By Cody Cooper, Crispy Clean Demolition · Published · Updated
Most demolition delays have nothing to do with the demolition. They come from steps that weren't started early enough: a permit, an inspection, or a utility disconnect. Here's the general order of operations for demolition in northern Utah. Requirements vary by city and change over time, so always confirm with your city and the relevant agencies.
1. Asbestos inspection
Utah's Division of Air Quality (DAQ) requires an asbestos inspection by a Utah-certified inspector before most demolition and renovation of buildings, including many residential projects. Asbestos was common in building materials for decades, including floor tile and mastic, ceiling texture, drywall joint compound, siding, roofing, and pipe and duct insulation. If the inspection finds asbestos-containing material, it must be removed by a certified abatement contractor before demolition. DAQ may also require a notification before demolition begins. Check DAQ's current rules for your specific project.
2. Utility disconnects
Before a building comes down, every utility has to be disconnected and made safe:
- Natural gas: contact your gas utility (Enbridge Gas serves most of northern Utah) to schedule a disconnect at the meter or main.
- Electric: contact your electric provider (Rocky Mountain Power in most of the area) to disconnect service.
- Water and sewer: your city or local district handles water shut-off and typically requires the sewer lateral to be capped, sometimes with an inspection.
- Other services: cable, internet, and phone lines should also be disconnected.
Some of these take time to schedule, so start them as soon as you know demolition is happening.
3. City demolition permit
Most cities in Davis, Weber, Wasatch, and Salt Lake counties require a demolition permit for buildings, and some also require one for detached garages and larger accessory structures. Permit applications often ask for proof of the asbestos inspection and utility disconnects. Properties in historic districts can have extra review steps. Your city's building department will tell you exactly what they need.
4. Blue Stakes (811) before digging
Before any excavation, including foundation removal, footing removal, and site grading, Utah law requires a call to Blue Stakes of Utah 811 so buried utilities can be located and marked. Locates take a few days to complete, so plan ahead.
5. Stormwater and site rules
Larger site disturbances may need stormwater controls, and some cities have rules about dust control, work hours, tree removal, and street cleanliness. Your contractor should know the local expectations and plan for them.
6. Demolition and haul-off
With the paperwork done, demolition itself is often the fastest part of the project. A typical house can come down and be hauled away in a few working days.
How Crispy Clean Demolition helps
We walk you through which steps apply to your property, the order to do them in, and who to call. We coordinate the asbestos inspection and abatement with certified professionals, confirm utilities are off before we start, and handle the demolition and haul-off ourselves. Request a free walkthrough or call 385-408-9910.
This guide is general information, not legal advice. Rules change. Confirm current requirements with your city, Utah DAQ, and your utility providers.